Feb 20, 2009 at 08:38 PM

PR WF for approval stuck in approvers inbox after manual approval in ME54

315 Views

We have Purchase Requistion (PR) Approval workflows, stuck in the approvers inbox as a User Decision step after the PR was manually approved. We know how to clear up previously stuck Tasks, when they should technically be complete using the standard WAPI.

1. What changes to the Workflow Template do we need, to ensure that in future when the BUS2105.RELEASED event is raised by application, that the associated tasks in user inbox are automatically removed ?

2. In the User Decision task definition itself (if you drilldown from the control tab) there is a tab for Terminating Events. What can this be used for ?

Thanks

Hari

PS - This is in R/3 46C