We are using Project- Make To Order.
I have attached the material "A" to WBS element & done MRP(e.g. on 17.02.2009). System generated PR & Planned Orer for the all Materials which are inthe BOM of "A".Purchase dept conerted PR into PO.
Today I have attached 1 one more material "B" to the same WBS element. & done the MRP Run again on the same WBS element. This time actually system should not generate the PR or Planned order for Material "A". It should generate only or "B". But the systeme is generated PR for the materials of "A".
Pl. help me for the same issue..
Thanks.