Overlapping

228 Views

I have two operations in routing

10 with labour time - 3 days

20 with labour time - 4 days

Option- required overlapping is maintained in 10 with min overlapp time of 1 day .

Then after forward scheduling iam getting following start dates.

operation 10 -- 19.02.2009

operation 20-- 19.02.2009

But why it is not considering min. overlap time and give start date of 20.02.2009 after considering min overlapp time of 1 day .

I dont want to maintain any Minimum Send-Ahead quantity