I have two operations in routing
10 with labour time - 3 days
20 with labour time - 4 days
Option- required overlapping is maintained in 10 with min overlapp time of 1 day .
Then after forward scheduling iam getting following start dates.
operation 10 -- 19.02.2009
operation 20-- 19.02.2009
But why it is not considering min. overlap time and give start date of 20.02.2009 after considering min overlapp time of 1 day .
I dont want to maintain any Minimum Send-Ahead quantity