_Scenario_
Move In - December
Meter Reading Results are entered for January and February. But, I dont want billing to happen for Jan and Feb. First Billing should happen only for month of March.
When Meter Reading Reason is given as 09 - (Meter Reading without billing) for Jan & Feb, as expected, billing documents are not created. But, when a periodic meter reading is taken for March, the previous two months consumption is also getting added to the March months billing document and it is getting posted as three different line items.
How to avoid accounting of Jan and Feb month meter reading? In March, when I run billing for March, only March month consumption must be taken into account.
Pls provide your valuable suggestion
Helpful answer will be awarded
Thanks
Vijay