WBS / Network of the PO

36 Views

Hi, if I have a PO that originated from PS that is not yet fully GR'd,

CASE 1: If I flagged the PO as delivery complete (by ticking the delivery complete button), will the WBS/network budget be re-open again and allow us to create a PO?

CASE 2: If I edited the PO amount and changed it to the same amount as the GR'd quantity, will the WBS/network budget be re-open again and allow us to create a PO?

Appreciate your help..