Hi, if I have a PO that originated from PS that is not yet fully GR'd,
CASE 1: If I flagged the PO as delivery complete (by ticking the delivery complete button), will the WBS/network budget be re-open again and allow us to create a PO?
CASE 2: If I edited the PO amount and changed it to the same amount as the GR'd quantity, will the WBS/network budget be re-open again and allow us to create a PO?
Appreciate your help..
Thanks,
Paula
Hi,
I assume that PR has got created by material assigmnet to activity in PS. In that case, budget will be available after changing material quantity in CJ20N.