WBS / Network of the PO

Hi, if I have a PO that originated from PS that is not yet fully GR'd,

CASE 1: If I flagged the PO as delivery complete (by ticking the delivery complete button), will the WBS/network budget be re-open again and allow us to create a PO?

CASE 2: If I edited the PO amount and changed it to the same amount as the GR'd quantity, will the WBS/network budget be re-open again and allow us to create a PO?

Appreciate your help..

Thanks,

Paula

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Feb 19, 2009 at 10:18 AM

    Hi,

    I assume that PR has got created by material assigmnet to activity in PS. In that case, budget will be available after changing material quantity in CJ20N.

    Regards

    Add comment