Project definiton, WBSE can be changed even if the status is set to CLSD

After setting the CLSD status of Project Def, WBS Elements as well Networks ,the fields project def.( PROJ-PSPID),Description(PROJ-POST1), responsible person(PROJ-VERNR), Applicant person(PROJ-ASTNR),start date(PROJ-PLFAZ),finish date(PROJ-PLSEZ), factory calendar(PROJ-KALID),Time unit(PROJ-ZTEHT),company code(PROJ-VBUKR), Business Area(PROJ-VGSBR), Plant(PROJ-WERKS),Location(PROJ-STORT), Profit center(PROJ-PRCTR) fields are open in project definition tab.

Also in case of WBS Elements, the fields WBSE description(PRPS-POST1),Project type(PRPS-PRART),short ID(PRPS-POSKI), responsible person(PRPS-VERNR), Applicant no(PRPS-ASTNR), responsible cost centre(PRPS-FKOKR), Req Cost center(PRPS-AKSTL),req Co Code(PRPS-ABUKR),,Planning element(PRPS-PLAKZ),Billing Element(PRPS-FAKKZ),Grouping WBS(PRPS-GRPKZ) are open in WBS Basic data tab page. Also fields of Assignment tab ,control tab, user fields tab are open. The screen shot of the same are attached for your ready reference.

Hence user can change these fields even after the project is closed

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Feb 19, 2009 at 09:38 AM

    Make use of user status to restrict changes when CLSD is set. Search for similar threads.