Dear all,
when runnig MRP the result sometimes has two or more PREQs/planned orders
on the same date. This is no problem if it is defined in this way by the planning
parameters like maximum lot size etc.
If this however is a result of demands which can not be covered in time, it is desired to have one
PREQ/planned order with the total quantity instead of having two or more on the same data.
Is there any customizing setting / user exit / BADI where it is possible to get this result ?
Thanks.
Hubert