Hello Experts,

Need one help to map the requirement for inbound process.

Material will arrive at GR Zone 9010----> Quality Inspection(Out of SAP)---->Final Storage types/BIN

Business have following requirements

1) Handling units should not be generated at any step, meaning Quantity level should be Bin level not at HU level. So, Product warehouse task should be created not HU WT in whole process. Business dont want to work with HUS.

2) After Inbound delivery distributions to WMS, Automatic GR should be done and WT should be created manually but confirmation step should be automatic.

Appreciate if you can just highlight the approach to map the requirement. I did some analysis and found that If we declare Quality inspection in Layout oriented storage control as ID point, i can work without HUs?

Is there any possible of direct Putaways to work with Product WT if I dont use any storage control?

Best regards

Shailesh Mishra