Dear all,

could you have a look at the question?

i created a project with several activities.

each activity has a work center.

there are two activity types ZLAB and ZOVH.

when i enter the planned hours for the activity,

i want to have the planned cost for these two activity types respectively.

how can i achieve it.

I did some tests. it seems that in the work center, just one activity type can be entered in the ActType Int.Proc. or this field will be blank.

how can i see the planned cost for two activity types ZLAB and ZOVH respectively??

thanks a lot.

Judy

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Use separate allocation cost elements (Category- 43) for both the activity types.

Regards

Former Member
0 Kudos

yes, the cost element category is 43.

Former Member
0 Kudos

both activity types should have separate cost elements

e.g. for activity type-1 it should be X and for activity type-2 it should be Y

Former Member
0 Kudos

U have to create two Workcenters as only one activity type can be maintained per work center.

In Project create 2 activity element for each activity type and assign relevant work cetner

Former Member
0 Kudos

it requires two workcenter as suggested.