Dear Experts................

Can any one plz explain the scenario of Network costing.

Process and steps.

Regards

Chandra

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • Best Answer
    avatar image
    Former Member
    Feb 19, 2009 at 04:26 AM

    Hi Chandra,

    You can plan project costs in two different ways:

    1.Manual cost planning in the WBS

    2.Cost planning using activities (network costing)

    When you plan dates and resources in network activities, the system determines the corresponding planned costs automatically.

    Planned costs are determined for the following objects:

    1.Activity inputs for internally-processed activities

    2.Primary costs for externally-processed activities and services

    3.Primary costs for general costs activities

    4.Primary costs for material components

    Please refer link as mentioned below for more details

    http://help.sap.com/saphelp_47x200/helpdata/en/df/561213c3c411d1ad990000e8a6353a/frameset.htm

    Regards

    Tushar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 19, 2009 at 04:12 AM

    hi

    create network in CN21.

    Create Network activities

    Internal

    External

    Primary

    assign the components or services to the activities

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 19, 2009 at 04:42 AM

    Hi,

    In addition to Tushar, U can also use CJ9K for Network costing (planned cost & payment).

    Regards,

    Shruti.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 19, 2009 at 04:22 AM

    dear chandra guru,

    you need to have costing variants for plannned and actual costs calculation

    the costing variants has valuation variants which contains data like from where cost has to picked up like for acitivity type -- we can mention fixed price ... for material cost --- moving average price or fixed price for MM master record ..... and costing variant controls how costs are executed and this contains costing type, valuation variant, cost component structure

    the cost component structure can be used for getting break cost details

    regards

    pushpa

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 19, 2009 at 04:50 AM

    Thanx to all.

    AP...PUSHPA...TUSHAR...SHRUTI.

    Regards

    Add comment
    10|10000 characters needed characters exceeded