Hi all,
We ran a material costimate with normal components FG>SFG>RM. The RM price Control is set to
V (Moving Average Price) and for SFG & FG it is S(Std. Price). After we run CK11N, the price for
RM in Material Master changes as per Moving Price. We found that the RM Component is
costed based on Standard Price and not on the previous cost run Moving Average Price. After
certain period, if we again do cost run, the sytem is again picking up the standard price for costing
not the revised Moving Price. We have checked the Valuation Variant in the Costing Variant, where the strategy given is 1. Moving Average Price 2. Standard Price. We also tried to change the
sequence as 1. Price as per Purchase Info Record 2. Moving Average Price and 3. Standard Price and
also 1. Standard Price and 2. Moving Average Price. Our requirement is when we run the cost estimate the raw material has to pick the price of previous moving price stored in the Material Master. Kindly tell us where to set the indicator.
Thanks,
Sadashivan