Hi Friends,
I am trying to create planned order and then trigger lead time scheduling for it.
I have maintained BOM, Routing, Production Version, and Scheduling Parameters for Planned Order as Detailed Scheduling with Scheduling Horizon as 50 days, and gactivated scheduling anf enerate capacity requirements in OPU5.
My Production Version is valid through 12/31/9999 and also validity in terms of order qty is correct.
I face problem of routing not being selected beyond the 70 days horizon.
I could not understand why the scheduling horizon considered is 70 days tough i have maintained 50 as scheduling horizon in OPU5.
Waiting for your valuable help and pointers
Regards,
Mayur