CHaRM-Is there any background job schedule to Transport

Hi Experts,

I have configured Change Request Management(CHaRM) in Solution Manager 7.0 EHP1.

Here is a scenario, after Tester successful test and change actions to "u201CConfirm Successful Testu201D from Actions. Then Change Manager change the status to "Release for Production" from Actions. Now the status change "Authorize to Import" and IT Operator / Basis Administrator "Import Correction to Production System" from Actions. And it's working fine.

Question is, Instead of IT Operator / Basis Administrator select "Import Correction to Production System" from Actions, is there any background job can schedule which will do the same work as IT Operator / Basis Administrator perform after CHANGE MANAGER's approval.

Solution Manager found program /TMWFLOW/SCMA_QUEUE_IMPORT, /TMWFLOW/SCMA_BTCH_SYNC_TEST, /TMWFLOW/SCMA_TRORDER_IMPORT but no use.

I will appreciate help.

Thanks

RS

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Feb 19, 2009 at 04:49 AM

    Hi,

    Your question leads to "MASS" Change of status of your Change Documents. To be more clear, if you say "Import Correction to Production System", it performs two actions

    1. The actual import into production

    2. Change the action of the Change Document to "Production" and additionally it may change the status of Change Request (if there is any status to be changed).

    There is no automatic way of scheduling this. It has to be done manually.

    Hope this answers your question.

    Feel free to revert back.

    -=-Ragu