Hi all,

I have a problem concerned to Production Process

Ex: Production Order of 5 finished goods need

Components: 10 qty x $20 = $200

Byproduct:(- 2) qty x $1 = -$2

SAP B1 calculate the production cost of 5 is 40 (200 divide 5). In my country, the production cost should 39.6 {(200-2)/5}.

Could you explain me why SAP calculated by first method instead of the second. What is different between two of calculation method. And how to solve my issues in SAP B1.

Thanks for your advice.

Regards,