Hello:

How can i create an automatic imputation for a material?

Regards.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Not yet

Former Member
0 Kudos

So, my question is:

Its possible to make compulsory that a material type NLAG always be charged against to a Cost Centre (Z....) ?

JL23
Active Contributor
0 Kudos

Default cost centers can be set in OKB9

but to my knowledge this will be a default for MM movements and not a default for purchase orders account assignment screen.

If you want defaults in a purchase order, then you may need to do some coding in a user exit.

Answers (1)

Answers (1)

Former Member
0 Kudos

imputation??

Former Member
0 Kudos

I mean if its possible to create a material and make compulsory that this material has to be charged for example to a Cost Centre (k)

Regards, and sorry for my english.

JL23
Active Contributor
0 Kudos

if you create a material with material type NLAG, which means it will not be stored, then the user is forced to enter an account assignment in the purchase order. so the costs will be charged to an account assignment (can be a cost center) when GoodReceipt and/or InvoiceReceipt is done

If you create a material of type UNBW, then you can manage stock by quantity, but value is consumed directly to cost center. the user is forced to enter an account assignment in the purchase order. so the costs will be charged to an account assignment (can be a cost center) when GoodReceipt and/or InvoiceReceipt is done

Former Member
0 Kudos

Simple! You check the material type you are using for that material.

Then goto OMS2 and remove the Value update for the plant in customization