How can I avoid changing a Purchase Req once released = ME52N
Thank
Goto OLME -> Purchase -> PR -> Release -> Assign indicator "1" to the release strategy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Change the changeability indicator to 1 for your release ID in customization. Then you cannot amend PR.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.