Hi Gurus,
I am trying to use the estimate method for progress analysis.
I have done all the necessary config like:
- defining progress version
- define statistcialkey figure for PoC
- assign measurement method as default(in this case 0000004)
Then i have gone ahead and assigned the progress version and default method in WBS/activites.
therafter i went into stimates tab at activity level and maintained the planned poc against the periods.
i confirmed the actvivity so that i can input actual poc also.
now i ran CNE1 and CNE5 to see the output.
however, i am not getting the PoC values that i have maintained.
any inputs on where i am going wrong. It would be of great help.
Thanks in advance..