Hi Gurus,

I am trying to use the estimate method for progress analysis.

I have done all the necessary config like:

- defining progress version

- define statistcialkey figure for PoC

- assign measurement method as default(in this case 0000004)

Then i have gone ahead and assigned the progress version and default method in WBS/activites.

therafter i went into stimates tab at activity level and maintained the planned poc against the periods.

i confirmed the actvivity so that i can input actual poc also.

now i ran CNE1 and CNE5 to see the output.

however, i am not getting the PoC values that i have maintained.

any inputs on where i am going wrong. It would be of great help.