Dear PS gurus
how we can reverse the network activity status which is already confirm.
ie if we confirm the network activity. is their any procedure to again revert back to its original status which was before
thanks in adv.
ANSAR
Hello,
SAP Guru
My problem , I had created all GRN and confirmed that particular network/ activity (i.e. 4000021/ 1768) which was created GRN material...but i want to reverse back that created GRN and credit in PO however due to confirmed activity this GRN material consumption in Project..so what will be the solution for reversed confirmed activity and created Fresh GRN...positive reply awaited.....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thnx all of uu..
its working..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Use transaction code CN29 to reverse / cancel activity confirmation.
Sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
use Tcode-CN29 to cancel the comfirmation of the activity.
give reason for cancellation.
Regards,
Shruti.
Edited by: Shruti Meti on Feb 18, 2009 9:03 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
You can go to cn41 and go to extra\envoirnment tab after selecting the activity and the go to confirm and select the cancle confirmation ,put reason and save then status is changed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.