Hi,
I have used the LTP for the header material. Now my scenario is I don't want any production but want to procure the raw materials. So for this I have copied the Stimulated dependent requirements of the raw material to PIR by using MS66 in active version 00.
Now , PIR for raw material is showing in MD62 and I run the MRP and Im getting the PR's against that PIR for raw materials.
Now my question is:
Is there any planning strategy by which I can consume the PIR at the time of GI or GR of the raw materials.
To consume the PIR for raw material either planned order or production order is required. And as soon as I GI the material against any production order the PIR should be consumed which is not happening with the strategy 40.
So please advice me by which planning strategy I can achieve this requirement.
I hope the requirement is clear but still if any more query you need please let me know so that we can have a discussion from the same platform.
I need this solution so that I can proceed further.
Regrads
Deepak Sharma