on 02-18-2009 6:52 AM
Hello All,
I have added a field on the IT 0000.
I want this field to be populated from data coming from IT 0105 , but I do not want that data to be stored in IT 0000. As it would cause duplication of data.
How can this be done.
Rohit
to populate a field in an infotype enhancement you have to do it PBO (process before output).
for example: transaction CMOD create project Zxyz, assign PBAS0001.
Create include ZXPADU01 for PBO enhancements and add coding there.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.