Dear all
could you help me on the following questions?
i created some projects and they are in process now.
i found that the basic start and finish dates (network and activities) were change. they are not fixed.
i hope they are not changing whatever i do.
using OPU6 i checked "specifying sheduling parameters"
i selected adjust basic dates, adjust dep. reqmnts to operation date and i ticked automatic scheduling.
i wondered if these two factors caused the basic dates change.
my second quesion is even i change the config above-mentined, those in-process projects will not be changed. that means their basic dates still changes.
how can i make the dates fixed when they are scheduled and saved for the first time.
thanks a lot
Judy