Wbs settlement to upper level WBS

Hello,

I have 4 level WBS .

all the expenses are settled at the 2 nd level.

so is there any way where i can determine that the cost of 4th level is to be settled at the 3rd and the cost of 3rd is to settled at the second to which i have give the settlement rule.

Waiting for response.

Regards

Vijay.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Feb 18, 2009 at 05:29 AM

    Assign IM to top WBS only and settle the lower WBS to its higher & so on. Finally settle top WBS to FXA. This is standard option for investment project. Settlement rule can be automatically generated using CJB2, you need to activate this option, i.e: create settlement rule to superior WBS.

    Regards,

    ANSAR

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 18, 2009 at 05:08 AM

    You can dirctly settle cost from 4th level WBS element to 2nd level WBS element by maintaining settlement rule with WBS element as reciever and reciver wbs element is 2nd level WBS element.

    Sudhir

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 18, 2009 at 05:43 AM

    Hi

    You can define the settlement rule in the WBS in which it is required.

    Go to the WBS, then edit -- > COst --> settlement -- > settlement rule

    Regards,

    Uddhab