Dear All,
I was created strategy based maintenance plan(frequency is 30 days) and mentioned call horizon 90% then schedule the maintenance plan amually using IP10.
I got the call objects like this
Plan date call date
20.03.2009 17.03.2009
19.04.2009 16.04.2009
I am expecting order 17.03.2009.where i can see the call dates