Hi
I need some inputs from you.
Even though i am having sub contracting stock ( ie., SC stock unrestr.), any new sub req are getting created in the unrestricted stock in turn creating new pur req, rather than using the SC stock that is available.
For Example:
Material B has
Unrestricted stock 20EA &
SC stock unrestr 500EA.
Now there is a sub req coming from the Parent material for 100EA.
Now, if i run MRP run on material B, its creating new pur req of 100 ea in the top (ie., unrestricted area), rather than consuming the SC stock that is available.
Please advise, how to set correct this.
Thanks
Kalyan