dear ps experts,
pl let me know whether projects materials consumed in project (ie., gr against nw pr-po done), can any where the same material shown as projects material inventory (virual)?
currently i am creating the automatic pr-material in network by using "n" item category, po is made against same pr and gr done against po, costs are posted in network, because mov type is 101.
my requirement is i wanted to show as inventory after gr done, is it possible,
why because, i wud like to raise sales order and do pgi and finally billing document.
is this possible or not? how this is achieved.
the above requirement is against customer projects scenario, pl help in guiding how this is possible in ps. my people for raising sales order/billing document, the same project materials are to be available in storage location accordingly pgi is possible.
withough pgi how the sales order/billing document is raised against the customer projects?
thanks in advance
srihari