Work center defined several times in a routing and causing an error

41 Views

Hi all,

I have been asked to create a work center that will act as a counter in routings. It should be selected together with each of three other work centers, which means that in some configurations the WC is selected 2-3 times. This works fine when testing in CU50, but causes following error in purchase order:

"Error while executing the specific scheduling module! (...)

Bucket xxx defined several times for position 000020 - > Check ranges!"