Hi All,
I am currently using ECC6, and have noticed the following for Budget Availability check:
If budget availability check is configured to check against the overall (planned) budget, the check (and warning/ error) will kick in at WBS level. However, when it is configured against the overall released budget, it will only kick in when the overall budget AT PROJECT level has been exceeded.
Can anyone confirm this?
Thank you very much.