Dear Experts,
In MCP1 report, what is Target Lead Time and Actual Lead Time. How it is calculated?
Thanks in advance for your valuable replies.
Regards,
Jejesh
Hi,
Target lead time
On the operation level, it is the time period between the scheduled
input date at the work center (target input) and the latest scheduled
finish of the operation.
The target input date is calculated through the scheduled execution
finish of the previous operation.
On the order level it is the time period between the scheduled start and
the scheduled finish.
and
Actual lead time
At operation level, the time between the input date at the work center
and the completion confirmation date (the total from queue time,
execution time and move time).
When calculating, the input date is determined via the completion
confirmation date of the preceding operation. The process-dependent
wait time of the preceeding operation is subtracted.
At order level, the time between the reported start date and the finish
date (the total from execution times and transit times of the operations
as well as the order floats before and after production).
Regards,
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Rajesh,
To understand the report I have created a new work center.
I have created routing with only one operation. Processing time per piece is one minute. I did not give any other standard values like setup labor etc. and also interoperation times are not given.
I have created a production order for 5quantity. So the production start date is today and it finishes with in 5min.
In this scenario. The lead time is 5min(for order). But why it is showing one day as Target leadtime?
Regards,
Jejesh