Target and Actual Lead time in MCP1 report

Former Member
0 Kudos

Dear Experts,

In MCP1 report, what is Target Lead Time and Actual Lead Time. How it is calculated?

Thanks in advance for your valuable replies.

Regards,

Jejesh

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member646433
Active Participant
0 Kudos

Hi,

Target lead time

On the operation level, it is the time period between the scheduled

input date at the work center (target input) and the latest scheduled

finish of the operation.

The target input date is calculated through the scheduled execution

finish of the previous operation.

On the order level it is the time period between the scheduled start and

the scheduled finish.

and

Actual lead time

At operation level, the time between the input date at the work center

and the completion confirmation date (the total from queue time,

execution time and move time).

When calculating, the input date is determined via the completion

confirmation date of the preceding operation. The process-dependent

wait time of the preceeding operation is subtracted.

At order level, the time between the reported start date and the finish

date (the total from execution times and transit times of the operations

as well as the order floats before and after production).

Regards,

Rajesh

Former Member
0 Kudos

Dear Rajesh,

To understand the report I have created a new work center.

I have created routing with only one operation. Processing time per piece is one minute. I did not give any other standard values like setup labor etc. and also interoperation times are not given.

I have created a production order for 5quantity. So the production start date is today and it finishes with in 5min.

In this scenario. The lead time is 5min(for order). But why it is showing one day as Target leadtime?

Regards,

Jejesh