Dear Friends,
In inspection type Task list usage is assigned
For Example
inspection type 01 - usage - 03
inspection type 05 - usage - 05
inspection type 06 - usage - 07
inspection type 10 - usage - 06
In my scenario i want to use all the above inspection type for a product
if i use mateial specification there is no any problem with my Task list usage
If suppose i use inspection plan do i need to create different inspection plan with different usage
or is it possible to create one inspection plan with all the above usage
what about universal usage 03 can i use it
i try to use but system does not triggering inspection lot
can any one Suggest some ideas
Many Thanks & Regards
Raj