Hi,
On R/3 material Master, for a material, we have maintained the ATP group as KP i.e No Check. For the KP check group configuration in SPRO "NO CHECK" flag is selected. (SPRO path: sales & distribution -> Basic functions -> Availability check and transfer of requirements -> availability check -> Availability check with ATP logic or against planning -> Define checking groups).
The expected result was that the system won't trigger ATP check for the material. But for some reason, system is triggering ATP check in APO. Any idea why is this happening? And is there anyway we can stop this ATP check?
In integration model the material has been selected. And we would have to keep it there because the material is part of some PPMs.
Thanks,
Alhad Pofali.