Hi Experts,
While confirmation using CO12- collective confirmation, i get a message "Total confirmed quantity does not equal planned quantity"( ECC6.0 system). Moreover for few plants, the yield is zeroed out, eventhough i enter the planned qty and after confirmation is executed, the yield shown is zero for those confirmed operations.
1. Why does the message "Total confirmed quantity does not equal planned quantity" appear eventhough i enter the planned operation quantity for confirmation?
2. Why does the yield quantity zeroed out for some plant? (maybe for some material also)?
Any pointers would be of great help.
Thanks,
SudhaharN
Dear
As Karthick said, go to OPK4, go to third tab, In quantities header tick mark for all entries.
In CO12 transaction click the Other view, now you can able to enter the order number, after enter the order number enter it, system will propose the quantities.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In OPk4, Confirmation parameters, for ur plant and order type combinaation, check the tab "operation indiv.entry initial screen. "
In that tick the Quantities PROPOSED..
u ll get away from the issue...
hope this helps..
karthick
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
10 | |
9 | |
5 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.