Skip to Content
0
Former Member
Feb 16, 2009 at 09:53 AM

Phontom Assembly

80 Views

HI,

A phantom assembly is typically used in multilevel 'Bill of Materials' (BOMs), where a single row of a phantom item serves the purpose of an entire sub-tree. Currently, these are being managed as subassembly items with an independent production process. While this approach works well in most instances, there are situations where the use of a phantom assembly would significantly reduce the amount of production orders being generated.Please advice if this feature can be implemented.

If yes can you please eloborate on the steps

Regards

Dhananjay