Hi

Total Up function not workin...

Budgeted for 2008 - 100 - WBSE X-R-1

2009 - 200 WBSE X-R-1

overall - 300 - WBSE X-R-1

these values are not getting totaled up for header level WBSE.

VenKx

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

you have to select all the wbs element

Edit --> Totalup tick on the annual as well as over all then check and save

Answers (1)

Answers (1)

venkatesh_kulkarni1
Active Participant
0 Kudos

did some R&D ... got the soln...

actually it was some profile & IM program settings