Dear Friends,

In our project Client wants to maintain more than one work centers for

one activity. So we proposed to maintain the activity elements, now

the problem is that we are confirming the activity elements but

activity is not getting updated. So for updating the activity we have

to do confirmation to the activity also and client wants to do the

confirmation only for activity element & not for activity.

The problem is if the activity is not confirmed the system will not be

able to do proper tracking of dates thru scheduling.

Is there any way out to solve this problem?