Former Member
Feb 16, 2009 at 04:36 AM

Scheduling in SAP-PS

912 Views

Hi all

Plz advice me for below senerio

We hv power plant. it will undergoing 15 days shutdown per year for preventive maintenance. this 15 day will be very critical.the plant should start on 16 days.now they are using Primevera for scheduling and monitoring 15 days day to day activities. The project hv 950 activities and they hv duration and relation ship. during 15days shut down period we will entering ( confirming) activities duration and rescheduling the project in primevera.

Plz suggest me is SAP PS advicible for above project for scheduling , monitoring and confirmation over primevera because we hv 950 activities.

regards

KP..