Hi ,
I am having issue where my planned delievry time is getting picked up starngely ..for the same material in different PO differnt planned delivery dates are captured though created on same day..one was created with PR and other directly..in my MMR and info record PDT maintined is 2 days and GR procesisng day as 1 day ...and i created PO on 13th feb .., in one it picked up delivery date as 16th feb and in other as 18th feb ..as in factory caleneder for me is having week edn as non working day..ie friday and saturday as off days and 14th and 15th feb are sat and sunday repectively