changing the batch number

Former Member
0 Kudos

Hi Gurus,

We have unrestricted stock in a batch. now there has arisen a need to change the batch number. Can that be done. Stock exists now.

Please let me know

Thanks

Anusha

Accepted Solutions (1)

Accepted Solutions (1)

csaba_szommer
Active Contributor
0 Kudos

Hi,

You can use MB1B + 311 (or MIGO + 311) where the sending and receiving storage loactions are the same. You can set the receiving batch during the posting.

Regards,

Csaba

Former Member
0 Kudos

I'm sorry i forgot to mention, the stock is in quality inspection right now and before the quality department can release it, we need a new batch number. can you please help

JL23
Active Contributor
0 Kudos

Cancel the goods receipt and redo it with correct batch number

csaba_szommer
Active Contributor
0 Kudos

Hi,

If your stock isn't in special stock segment (sales stock ,project stock) I don't think you could solve it without removing it from QI stock type.

If your stock got to QI stock type as a consequence of GR you should follow Jurgen's advice (this involves two step: cancel GR (MBST/MIGO(PO) or CO13(PrdOrd)) and new GR(MIGO/CO15)). If not, you can solve it only three step I think (post to unrestricted > SLoc-Sloc transfer, with same SLoc > post to QI with proper batch number).

Regards,

Csaba

Former Member
0 Kudos

Hi Jurgen,

a quick question. There are lot of other line items in that material doc. so are these the steps that i need to follow

1) go to MIGO, can mat doc and when i enter the mat doc no it brings up all the line items, i just need to select the line item that i 'm looking to cancel, select tat line item and save the doc. now do the MIGO again against a PO and then just receive just that quantity with the new batch number and that should be it right

Thanks

anusha

Edited by: anusha vemulapati on Feb 13, 2009 4:42 PM

JL23
Active Contributor
0 Kudos

yes

Former Member
0 Kudos

This does not work. The stock is in quality inspection right now. and we need another batch berfore quality dept can release it into unrestricted stock

Former Member
0 Kudos

Hi,

Is there any problem if u change the Batch after it is approved by the Qulaity.

After the UD u immediately changed the Batch in MB1b 311 Mvt type.

Biswajit

Answers (4)

Answers (4)

raghavendra_praveen
Active Contributor
0 Kudos

Hi

you an change batch number by transfer posting using 309 ..also check in OMCQ - message number M7/199 should be set as warning message otherwise you cannot do it.

Thanks

Former Member
0 Kudos

You can change batch number from MIGO by 309 movement.

Former Member
0 Kudos

you can change it by 411 movement type and there you get the option of issuing batch and reciving batch

Former Member
0 Kudos

Hi,

Use MIGO transfer posting with mvt 309.

MdZ