Hi Gurus,

my client is entering the back log data he is entering sales order for the date of 22.08.2008 ( he has given req del date, pricing date as 22.08.2009 ) and saved sales order.

Now he is trying to delivery and pgi by giving the act pgi date as 22.08.2008 but the system is giving error message i.e deficit of sl unrestricted use 89.509 pcs but our delivery quantity is only 45 pcs and the material is available in the respective storage location with 47 pcs

and at the same time the staging date in delivery is changed to todays date

in previous deliveries the staging date is equal to the act delivery date and for those deliveries there was no problem

what could be the problem in the present delivery

thnaks