I have read a document for Go Live activity, where written that
Step ; 1 Update Standard prices of Semi finish and finish material thru MR21
Step ; 2 Upload the above materials stock and then
After the stock is uploaded into the system, the standard cost estimate will be
marked and released into the material master using transaction code CK40N.
Is this experts recommendation, If I done Step 1 and costing run CK40N use till marking not release to check material prices. Is it will be OK.
thanks