I already have 0FI_AR_4 in production and it's loading deltas everyday, now I need to enhance it by adding 1 new field, my questions when I move this new enhanced extractor to production again, its necessary to clear SMQ1/RSA7 with users locked beforee the transport? and whey?

Thank you for your help.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

avatar image
Former Member Nov 10, 2016 at 12:24 PM
0

Hi,

please try to transport your changes to production system at non business hours or weekends where there is no business.

Before doing transport to production, please load all delta data(twice) into bw until you get 0 at RSA7 and PSA.

if we do transports on weekends or non business hours then we don't need any user lock. but be sure no transactions are recording during your transports which are related to your data source.

Thanks.

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Nov 10, 2016 at 03:38 PM
0

Hi

regarding the 0FI_ enhancement

if you want to have your new field filled also for the historical data you need to delete the old requests and reload with init / delta process . If you dont want to lock ECC users reload by night -

if you want simply to have the new field filled with the new data ( new requests after the modification ) you don't need to reload requests .