Dear All,

At our client site they are starting their production planning after receiving sales order. Their scenario is make to order. but the important thing is as follows: After receiving sales order they are starting designing their Finished Product & then design department creates the order BOM after finishing design process. this process takes around 2 to 3 months after creating sales order. So till then could not create order BOM & hence this material cannot be planned in MRP. But some of the standard materials(external procurement) they start purchasing form vendor as they are having long planned delivery time.

So please tell me how to map this plan in SAP? How it could be done without having BOM through MRP?