Hey Gurus,
We are using strategy 50 for our top level materials because we have top level materials that have components that are associated with sales order stock. I have noticed that strategy 50 is not consuming the planned independent requirements or I can't seem to see where it is consuming if it is.
The consumption mode we are using is 2 and we are using backward and forward consumption per as 30 for each and we have planned independent requirements populated in weekly buckets.
I know that strategy 40 works well for sales order demand consumption but we want strategy 50 to work similiarly to this because of our sales order stock components. Do you gentlemen have any suggestions as to how we can see this consumption being taken place using strategy 50?
Sincerely,
Nina