on 02-10-2009 11:56 AM
hello!
i am evaluating rescheduling functionality in SAP (V_V2). rescheduling works, but it does not consider dependent requirements from planned orders.
i have following situation
- stock 7 pc
- 1.3. cusord -5pc -> confirmed
- 5.3. depreq -2pc
- 10.3. cusord -2pc -> confirmed
i would expect that the second customer order is not confirmed, as i do have an earler dependent requirement. in customizing of checking rule 'A' dependent requirements are included.
thanks for help!
matthias
Hi,
Can u please explain in detail, what exactly ur looking. whether u want to assing the qty which were blocked earlier to confirmed.
bye
Anil