Skip to Content
0
Former Member
Feb 10, 2009 at 04:11 AM

Question on STO

15 Views

I have a STO process between 2 plants "A" & "B" without shipping (or sales and distribution involved, use "351" to In-transit and receive using 101). The problem is when I'm creating STO from Plant "A" to Plant "B", it is shows up in Stock requirement list of Plant "A" but does not have anything on Stock requirement list of Plant "B" which is technically wrong.

I'm missing something in config for inter-plant movements (without SD) from MRP perspective. Can anyone let me know why it is showing up on stock requirement list of Plant "A" and not on the other plant. What needs to be configured to fix this issue. Please help me ASAP. Thanks in advance.