Hi friends
Do we have a standard report that gives total number of labour hours (activity type) per work center for a particular period.
Thanks
Hi Reena,
Check reports - MCP1 & MCP7, also COOIS with operations / confirmations as selection parameter on initial screen.
If helpful award points
Regards,
Vivek