Former Member
Feb 09, 2009 at 03:57 PM

Planned Order Schedule Date Overlap

183 Views

Hi

I have an issue with Planned Orders generated by the MRP run when itu2019s run with u201CLead Time Scheduling and Capacity Planningu201D. I have two planned orders one dependant on the other (Multi Level BOM) however there is an overlap between the Schedule Finish Date of one order and the start date of the other order. I donu2019t know of any settings which would cause an overlapping between planned orders. I would expect to see the one planned order scheduled to start immediately after the other orderu2019s schedules finish date (not before).

Does anyone know if there is configuration causing this?