Hi,
i have one project with large numbers of wbs elements for that, i have split the project structure into different chilld projects.
there is one parent project where all budget value enter at root level wbs element. when i made the actual cost aganst the parent project the system shows assigned values against the top level wbs elenment. the problum arrise when i transfer the actual cost by primary or secondary cost element to the child projects, the assigned values in the parent project reduces with the same sender wbs element amount.
Is there any way the assignment remains in the root wbs elements either by any of the transaction reposting, allocation, settelment etc.
kindly help i will award points
regards
saqib usman