Hi PP GURUS,
NEED SOME GYAAN!!
What are the major integration settings for a typical PP-PS scenario.
Ellaborate answers will be rewarded
THNX in Advance
HKR
Hi Hemanth
with respect to your query i want to give brief overview reg PP ps
while creation of BOM (wbs/material) with tcode cs01 and cs71 you have to select usage as 3
you have to create project with tcode cj20n and assign budget and cost planning is to be done
activity is to be assigned to net work
once it is done you have to run Project Mrp with tcode as MD51 select for mrp paramters enter Project and WBS element as well
whenever you are going to convert material bom to wbs bom you have to use t code cn33 for bom transfer
this scenario will be useful where project execution is going on but the requirements comes through project mrp it will be convert planned order to production order (md04) as well as purchase requisitions
i hope this will clarify you an overview relates to PP and PS integration
thanks
shaik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As i know
1)
BOM should be created with BOM usage 3(Universal). Because these BOM transfer to required project.
2)
In the project, below project two components WBS and Network, you can attach components(Raw materials) to WBS as well as Network.
If u attach the components to WBS these components are planned with respect the project system.
Run the MRP at project level. The material procured(attached to WBS) are resever against the project showing as project stock.
3)
The component which are attached to network are planned at plant level. the components are plant stock.
Regards
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.