Former Member
Feb 08, 2009 at 01:50 PM

MRP Scheduling

20 Views

Dear All,

I have a Finished Good that consists of 2 semi finished

Now I run MRP

FG Start Date: 15.03.2009 Finish: 16.3.2009

SEMI1 Date: 08.03.2009 Finish: 15.3.2009

SEMI2 Date: 04.03.2009 Finish: 15.3.2009

Shouldn't the FG start date be the earliest date for the semi like

Start: 04.03.2009 and Finish 16.3.2009 ?