cancel
Showing results for 
Search instead for 
Did you mean: 

MRP Scheduling

Former Member
0 Kudos

Dear All,

I have a Finished Good that consists of 2 semi finished

Now I run MRP

FG Start Date: 15.03.2009 Finish: 16.3.2009

SEMI1 Date: 08.03.2009 Finish: 15.3.2009

SEMI2 Date: 04.03.2009 Finish: 15.3.2009

Shouldn't the FG start date be the earliest date for the semi like

Start: 04.03.2009 and Finish 16.3.2009 ?

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Check the setting of OPU3 for Adjust scheduling.

Adjust dates in lead time scheduling :- 1 Adjust dates to order start.

It is possible if the routing having two operation one SFG1 and SFG2. You will get the result as you want.

But if you are having different order for SFG1 and SFG2 then you will get the same result as per order date of semifinish material. As material should available at order start. FG start date will be the finish date for dependent requirement.

Hope clear to you.

Regards,

R.Brahmankar

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Rafik,

Based on what i see, it is OK, i think the set up is backwards scheduling & hence the system has proposed those dates.

If you need any more clarifications, please provide - the need date for the FG, PLDT / Inhouse Prod time, GR for FG & SEMI1 & 2.

If helpful award points

Regards,

Vivek

Former Member
0 Kudos

Hi,

FG Start Date: 15.03.2009 Finish: 16.3.2009

SEMI1 Date: 08.03.2009 Finish: 15.3.2009

SEMI2 Date: 04.03.2009 Finish: 15.3.2009

as i see that the semi1 and semi2 will be available at 15.3.2009

and it will gi to produce fg

i dun see any problem here

you should also consider which scheduling u used : basic or lead time

if you used basic then inhouse prod time is taken into consideration

if you used lead time you can check routing

anyway consider safety time, scheduling margin key for the distubance on shop floor as i see

you schedule is very tight between semi1,semi2 and fg

i hope it helps

best regards,

freddy